Loon Mountain Bridge Replacement On Track

The Loon Mountain Bridge replacement project is on track. The project originally called for construction throughout a full two year period.  However, at this point contractor R.M. Piper is able to take a break this winter with completion of the project next fall.  HEB is providing full-time resident engineering and recently used Dragonfly Aerials to do mid-construction overflight of the project.  As you can see, the piers andabutments for the new bridge are nearly complete.

Placing the steel, the next major step, is scheduled for November/December.  For more information, please contact Chris Fournier, Lead Structural Engineer, at cfournier@hebengineers.com or (603) 356-6936.